Who is responsible for determining how tasks will be done in a weak matrix project management structure?

Respuesta :

BenitoMarin BenitoMarin
  • 25-01-2020

Answer:

The correct answer is: The functional manager.

Explanation:

A weak matrix project management structure is the type of business organization managed by two executives: the functional manager and the project manager. Both of them work jointly and report to each other accordingly. Out of the two of them, the functional manager is in charge of controlling how work is done within the firm.

Answer Link

Otras preguntas

Do u get Bitesize in America, India, Australia and China?
Connie invested $3,250 in a regular savings account thatpaid compound interest at a rate of 7.5% per year,compounded monthly. How much was her investment worthi
Please help asap!!!!!!! Please quick!!!
it's important to buy a business computer rather than a personal computer because​
What advice on high school can you give for sophomores?
Who is the first man climb mount everest​
Ghee are not should be........... (from health)​
Please help me with this answer please thank you
how does hydroelectric dam impact the enviroment?​
The latent heat of vaporization of water is 540 calories/gram. How many calories are required to completely vaporize 500 grams of water? 1,040 cal 40 cal 270,0