seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

between which two consecutive integers does 173 lie? Answer: A. 10 and 11
How did geography affect life and the economy in the Middle Colonies?
Sophina brought 3 yards of trim to put around a rectangular scarf. She does  not want the scarf to be wider than 12 inches or narrower than 6 inches .Using whol
How did Roosevelt's policies help the conservation of natural resources?
what is the solution to the equation? 3/4 x =12 Answers: A. 9 B. 48 C.16 D.36
seven less than the product of twice a number is greater than 5 more the same number which integer satisfies this inequality
what is the degree measure of the acute angle formed by the hands of a 12-hour clock that reads exactly 1 o'clock?
The document that described the first government of the united states of america was called the
Two friends share 1/4 gallon of lemonade equally.What fraction of the gallon of lemonade does each friend get?
Which of the following is not capable of reacting with molecular oxygen? A. SO₂ B. SO₃ C. NO D. N₂O E. P₄O₆