The transportation department is resurfacing 12.75 miles of roadways in Narvarro Country. The crew completes work on a 1/8-mile section of roadway each hour. How many hours will it take to complete the resurfacing project

Respuesta :

Answer:

102 hours

Step-by-step explanation:

That would be 12 3/4 divided by 1/8   hours

= 51/4 / 1/8

= 51 * 8 / 4

= 408 /   4

= 102 hours