There are four activities on the critical path, and the standard deviations for their durations are 7, 15, 31, and 6 days. The standard deviation of the duration of the critical path is: a. 1271 b. 35.65 c. 59 d. 7.681 e. 14.75

Respuesta :

Otras preguntas

If a 18 25 fl oz bottles cost $144.00 how much does one bottle cost?​
What are the mutual benefits for First Nations people and Europeans were consequences of the fur trade
The probability of choosing the letter G and flipping tails is...
If you happen to deal with people whose beliefs are different from you, how are you going to explain yourself to them without being rude and without falling in
How can old generations able to attend school​
Juan is making t-shirts to sell at a concert. The cost of making the shirts is $50 plus $7.50 per t-shirt. He will sell them for $15 each. What is the minimum n
pls help my its now due in 20 minutes
A popular dance club allows 29 customers to enter per hour. The club has to keep their occupancy below 600 at any time during the day. Currently, the club has 3
The figure below is a square. If m2AEB = (5x + 15)°, what is the value of x?
what is bigger 95.58 or 95.850